A number of the imported components have just arrived at Nu Lines warehouse. These will be delivered to Arnhem for storage during the course for November.
Installation of the first lift is schedule to start on the 15 January 2018. This will prevent any new lift construction disruptions during the festive season and will allow both lifts to remain in service during the busy period.
The full installation schedule is available to view here.
Lift number 2 will be replaced first. All parts will be kept as spares for lift 1 for the duration of project.